您好,欢迎来到济南通宇恒成自动化工程有限公司网站!

服务热线

当前位置: 首页- 新闻中心 > 客户见证
常见问题
新闻中心

MNS低压配电柜安装规范是什么?

发布时间:2021-05-17 来源:http://www.tongyuhengcheng.com/ 浏览量:

1.安装前对准备工作的检查
1. Check the preparation before installation
在安装前,MNS低压抽屉柜监理工程师及甲方工程师要检查进场道路是否畅通,必要时要求要求总包单位修建简易运输通道与各安装点连接,施工场地布置应满足文明施工的要求。同时还应检查安装单位的施工机具安排状况,督促安装单位对施工机具进行检查,确保状态良好。压设备到达现场前,配电室、地沟、基础槽钢应已完全竣工
Before installation, the supervision engineer of MNS low-voltage drawer cabinet and the engineer of Party A shall check whether the access road is smooth. If necessary, the general contractor is required to build a simple transportation channel to connect with each installation point, and the construction site layout shall meet the requirements of safe and civilized construction. At the same time, the arrangement of construction machines and tools of the installation unit should be checked, and the installation unit should be urged to check the construction machines and tools to ensure that they are in good condition. Before the pressure equipment arrives at the site, the distribution room, trench and foundation channel steel shall be completely completed
1)、配电室
1) . distribution room
配电室:配电室施工前,低压配电柜要将建配电室所需的详细图纸交予施工方(合同签订后2周内,重 点要落实客户对图纸的位置、内容、完成时间确认),并且在配电室建设过程中,我方或协作单位的技术人员要在现场监督,避免施工错误。(配电室建设大约需2周左右)
Distribution room: before the construction of the distribution room, the low-voltage distribution cabinet shall submit the detailed drawings required for the construction of the distribution room to the construction party (within 2 weeks after the signing of the contract, the key point is to confirm the location, content and completion time of the drawings by the customers), and during the construction of the distribution room, the technical personnel of our party or the cooperating unit shall supervise on site to avoid construction errors( It will take about 2 weeks to build the distribution room)
                           MNS低压抽屉柜
2)、地基:MNS低压抽屉柜槽钢安放位置要与配电室预留的设备风道相对应,设备离墙的小距离要明确(距离太近,设备的柜门打不开)。(槽钢焊接大约需2天,我方技术人员必须到场指导)
2) Foundation: the channel steel of MNS low-voltage drawer cabinet should be placed in the position corresponding to the equipment air duct reserved in the power distribution room, and the small distance between the equipment and the wall should be clear (the distance is too close to open the cabinet door of the equipment)( It takes about 2 days to weld the channel steel, and our technicians must be present for guidance.)
设备到达现场:
Equipment arrival at site:
3)、若配电室、地基若未建好,低压配电柜设备要有存放位置(要防雨或提供必要的防雨材料)。
3) If the power distribution room and foundation are not built, the low-voltage power distribution cabinet equipment should have a storage location (rain proof or provide necessary rain proof materials).
2.安装
2. Installation
2.1各配电房门窗须严密,低压配电柜房内清洁。
2.1 the doors and windows of each distribution room shall be tight, and the low-voltage distribution cabinet room shall be clean.
感谢您的阅读,希望以上内容对您有所帮助,如您想了解更多精彩内容请点击我们的官网:MNS低压抽屉柜http://www.tongyuhengcheng.com
Thank you for reading, hope the above content is helpful to you, if you want to know more wonderful content, please click our official website: MNS low voltage drawer cabinet http://www.tongyuhengcheng.com .
首页首页 产品产品 电话电话 置顶置顶